Project Schedule

  • 6/2/10 – Notice of Award
  • 6/15/10 – Notice To Proceed
  • 6/22/10 – Complete Demolition Work and Stripping Top Soils
  • 7/9/10 – 7/30/10 – Land Lease Delay
  • 8/2/10 – River City Mobilized on Site
  • 8/16/10 – Complete Test Cell Building Pad
  • 8/25/10 – Complete Rammed Aggregate Piers at Test Cell Building
  • 9/23/10 – Completed 95 % of Grade Beams at Test Cell
  • 9/23/10 – River City completes 23 Equipment Pads in Education Building
  • 9/23/10 –  River City starts Grade Beams at Education Building
  • 9/30/10 – Underground Sanitary, Sprinkler and Storm Completed in Test Cell Building
  • 10/1/10 –  Fleet Storage Building Pad Completed
  • 10/1/10 – Start MEP Underground Piping and Conduits at Education Building
  • 10/4/10 –  Mathis starts Site Manholes and Storm Systems
  • 10/6/10 –  Sub Surface starts Rammed Aggregate Piers in Fleet Storage Building
  • 10/11/10 – Rammed Aggregate Piers Completed in Education Building
  • 10/13/10 – Start Concrete Walls in Test Cell Building
  • 10/13/10 – River City Starts Grade Beams in Quad C at 12 line
  • 10/18/10 – Sub Surface Completes Rammed Aggregate Piers at Fleet Storage Building
  • 10/21/10 –  Sub Surface Completes All Project Rammed Aggregate Piers
  • 10/25/10 –  River City Pours Exterior Grade Beam at Quad J, 23 line
  • 11/09/10 –  Vee-Jay Cement Contracting starts under slab rock in Quads A & D
  • 11/22/10 –  Martin Electric starts branch conduits in Quad A &D
  • 12/09/10 –  River City starts pouring Fleet Storage Grade Beams
  • 12/10/10 – Critical Path Milestone – Delivery of ED Bldg. Structural Steel
  • 12/10/10 –  Poured Slab On Grade for Quad A & D
  • 12/21/10 – River City completes 8,143’ (Mile & a half) of grade and tie beams at ED Bldg
  • 01/13/11 – River City revises schedule to reflect steel, slabs and rock delays
  • 01/18/11 –  River City completes footings and foundations  to Fleet Storage
  • 01/19/11 –  Glover Mays unloads 1st delivery of ED Bldg. Bar Joist
  • 01/28/11 – Vee-Jay Cement Contracting pours Quad B slab
  • 01/31/11 – Egyptian Electric energizes all transformers for temporary power
  • 02/04/11 – Martin Electric completes branch conduits in Quad B, starts Quad B & C, E-F
  • 02/14/11 – River City pours last Test Cell walls and completes foundation to Fleet Storage
  • 02/15/11 – Vee-Jay Cement Contracting pours Quad C, between AA & E
  • 02/16/11 – River City starts Water Tank and Pump House grade beams
  • 02/16/11 –  Diecker Terry Masonry starts masonry in Test Cell Building
  • 02/21/11 – Bush & Sons completes site water lines to all three buildings
  • 03/02/11 – Vee-Jay pours Quad B & C, between E & G line
  • 03/02/11 – Glover Mays completes structural steel in Test Cell Building
  • 03/04/11 – Glover Mays unloads Quad B steel
  • 03/07/11-   Vee-Jay pours Quad J slab
  • 03/11/11 –  Martin Electric completes branch conduits in Fleet Storage
  • 03/18/11 –  Glover Mays completes erection of Quad D structural steel
  • 03/24/11 –  Vee-Jay pours Fleet Storage Building slab
  • 04/08/11 –  Martin Electric completes branch conduits in Quad D
  • 04/12/11 –  Diecker Terry Masonry completes main walls to Test Cell Building
  • 04/13/11 –  Quad E steel over Penthouse arrives
  • 04/22/11 –  River City received Door Frames for Quad A, B & C
  • 04/29/11 –  Grover Mays unloads last 5 loads of steel for Quad E
  • 04/29/11 –  Vee-Jay pours Quad D slab from 5-6 & E-G line
  • 05/03/11 – Vee-Jay pours 2nd floor deck to Quad A & B
  • 05/04/11 –  Vee-Jay completes Quad D Service Lab 1 pour
  • 05/10/11 –  Vee-Jay completes Test Cell Building slab
  • 05/10/11 –  Grover Mays starts the Fleet Storage Building steel erection
  • 05/10/11 –  A & K Specialty starts interior & exterior steel studs work in ED Bldg
  • 05/17/11 –  Vee-Jay pours  Quad E slab on grade between 9-11 line
  • 05/18/11 – Grover Mays & Sons complete steel erection at Fleet Storage
  • 05/25/11 – Grover Mays & Sons starts erection of Quad C steel
  • 06/02/11 _  Vee-Jay pours Penthouse deck slab in Quad E
  • 06/06/11 –  Grover Mays & Sons complete erections of Quad C Structural Steel
  • 06/07/11 –  Southwestern Sprinkler Service mobilized / starts Quad
  • 06/10/11 –  Vee-Jay pours Quad E, Service Lab #2 slab on grade
  • 06/15/11 –   Grover Mays & Sons complete erection of Quad F structure
  • 06/17/11 –   Diecker Terry Masonry starts brickwork in Quad A, East elevation
  • 06/24/11 –   Grover Mays & Sons complete erection of Quad J structure
  • 07/07/11 – Vee-Jay poured Quad C, 2nd floor deck.
  • 07/29/11 –   France Mech., SIP & Southwest Sprinkler receives most of their equipment
  • 08/08/11 – Kehrer Bros. Roofing completes roofing the Test Cell Building
  • 08/09/11 – Vee-Jay completes pouring all of Quad F floor slabs
  • 08/11/11 – Grover Mays & Sons completes Quad E, Mechanical Penthouse roof deck
  • 08/18/11 – Kehrer Bros. Roofing has covered roofs in Quads A, B, D & E Penthouse
  • 08/23/11 – East Iowa Deck Supports starts metal panels at the Test Cell Building
  • 08/26/11 –   Grover Mays & Sons completes Quads F & J roof deck
  • 08/26/11 –   Kehrer Bros. completes Quads C (high roof), Penthouse &Quad D roofs
  • 09/02/11 –   Litton Enterprises completes roof storm lines in Quads A, B, C, D & Pent
  • 09/19/11 – A & K Specialty starts drywall work in Quads A & B, 2nd floor
  • 09/23/11 –   Kehrer Bros. Roofing covers Quad C (low roof)
  • 09/30/11     Kehrer Bros. Roofing covers Quads J, F & E
  • 09/30/11 East Iowa Deck Supports installs Metal Panels to Test Cell Building
  • 10/05/11 East Iowa Deck Supports starts Metal Panels to the Education Building
  • 10/12/11 Southwestern Sprinkler Service test sprinkler piping in Quads A, B & D
  • 11/18/11 E. T. Simonds Construction Company started rocking West of ED Bldg
  • 11/21/11 Automotive Technology completes In-Ground Vehicle Lifts
  • 11/22/11 Ron Ward Painting starts painting in Quads A & B
  • 12/02/11 Kerher Bros. Roofing completes roofing of all buildings
  • 12/19/11 Southern Illinois Piping sets Chillers in Outside Mechanical Space
  • 01/03/12 Diecker- Terry Masonry start interior block walls in Automotive areas
  • 07/17/12 – Substantial Completion
  • 10/15/12 – Final Completion
  • 12/31/13 – Established Contract End Date