- 6/2/10 – Notice of Award
- 6/15/10 – Notice To Proceed
- 6/22/10 – Complete Demolition Work and Stripping Top Soils
- 7/9/10 – 7/30/10 – Land Lease Delay
- 8/2/10 – River City Mobilized on Site
- 8/16/10 – Complete Test Cell Building Pad
- 8/25/10 – Complete Rammed Aggregate Piers at Test Cell Building
- 9/23/10 – Completed 95 % of Grade Beams at Test Cell
- 9/23/10 – River City completes 23 Equipment Pads in Education Building
- 9/23/10 – River City starts Grade Beams at Education Building
- 9/30/10 – Underground Sanitary, Sprinkler and Storm Completed in Test Cell Building
- 10/1/10 – Fleet Storage Building Pad Completed
- 10/1/10 – Start MEP Underground Piping and Conduits at Education Building
- 10/4/10 – Mathis starts Site Manholes and Storm Systems
- 10/6/10 – Sub Surface starts Rammed Aggregate Piers in Fleet Storage Building
- 10/11/10 – Rammed Aggregate Piers Completed in Education Building
- 10/13/10 – Start Concrete Walls in Test Cell Building
- 10/13/10 – River City Starts Grade Beams in Quad C at 12 line
- 10/18/10 – Sub Surface Completes Rammed Aggregate Piers at Fleet Storage Building
- 10/21/10 – Sub Surface Completes All Project Rammed Aggregate Piers
- 10/25/10 – River City Pours Exterior Grade Beam at Quad J, 23 line
- 11/09/10 – Vee-Jay Cement Contracting starts under slab rock in Quads A & D
- 11/22/10 – Martin Electric starts branch conduits in Quad A &D
- 12/09/10 – River City starts pouring Fleet Storage Grade Beams
- 12/10/10 – Critical Path Milestone – Delivery of ED Bldg. Structural Steel
- 12/10/10 – Poured Slab On Grade for Quad A & D
- 12/21/10 – River City completes 8,143’ (Mile & a half) of grade and tie beams at ED Bldg
- 01/13/11 – River City revises schedule to reflect steel, slabs and rock delays
- 01/18/11 – River City completes footings and foundations to Fleet Storage
- 01/19/11 – Glover Mays unloads 1st delivery of ED Bldg. Bar Joist
- 01/28/11 – Vee-Jay Cement Contracting pours Quad B slab
- 01/31/11 – Egyptian Electric energizes all transformers for temporary power
- 02/04/11 – Martin Electric completes branch conduits in Quad B, starts Quad B & C, E-F
- 02/14/11 – River City pours last Test Cell walls and completes foundation to Fleet Storage
- 02/15/11 – Vee-Jay Cement Contracting pours Quad C, between AA & E
- 02/16/11 – River City starts Water Tank and Pump House grade beams
- 02/16/11 – Diecker Terry Masonry starts masonry in Test Cell Building
- 02/21/11 – Bush & Sons completes site water lines to all three buildings
- 03/02/11 – Vee-Jay pours Quad B & C, between E & G line
- 03/02/11 – Glover Mays completes structural steel in Test Cell Building
- 03/04/11 – Glover Mays unloads Quad B steel
- 03/07/11- Vee-Jay pours Quad J slab
- 03/11/11 – Martin Electric completes branch conduits in Fleet Storage
- 03/18/11 – Glover Mays completes erection of Quad D structural steel
- 03/24/11 – Vee-Jay pours Fleet Storage Building slab
- 04/08/11 – Martin Electric completes branch conduits in Quad D
- 04/12/11 – Diecker Terry Masonry completes main walls to Test Cell Building
- 04/13/11 – Quad E steel over Penthouse arrives
- 04/22/11 – River City received Door Frames for Quad A, B & C
- 04/29/11 – Grover Mays unloads last 5 loads of steel for Quad E
- 04/29/11 – Vee-Jay pours Quad D slab from 5-6 & E-G line
- 05/03/11 – Vee-Jay pours 2nd floor deck to Quad A & B
- 05/04/11 – Vee-Jay completes Quad D Service Lab 1 pour
- 05/10/11 – Vee-Jay completes Test Cell Building slab
- 05/10/11 – Grover Mays starts the Fleet Storage Building steel erection
- 05/10/11 – A & K Specialty starts interior & exterior steel studs work in ED Bldg
- 05/17/11 – Vee-Jay pours Quad E slab on grade between 9-11 line
- 05/18/11 – Grover Mays & Sons complete steel erection at Fleet Storage
- 05/25/11 – Grover Mays & Sons starts erection of Quad C steel
- 06/02/11 _ Vee-Jay pours Penthouse deck slab in Quad E
- 06/06/11 – Grover Mays & Sons complete erections of Quad C Structural Steel
- 06/07/11 – Southwestern Sprinkler Service mobilized / starts Quad
- 06/10/11 – Vee-Jay pours Quad E, Service Lab #2 slab on grade
- 06/15/11 – Grover Mays & Sons complete erection of Quad F structure
- 06/17/11 – Diecker Terry Masonry starts brickwork in Quad A, East elevation
- 06/24/11 – Grover Mays & Sons complete erection of Quad J structure
- 07/07/11 – Vee-Jay poured Quad C, 2nd floor deck.
- 07/29/11 – France Mech., SIP & Southwest Sprinkler receives most of their equipment
- 08/08/11 – Kehrer Bros. Roofing completes roofing the Test Cell Building
- 08/09/11 – Vee-Jay completes pouring all of Quad F floor slabs
- 08/11/11 – Grover Mays & Sons completes Quad E, Mechanical Penthouse roof deck
- 08/18/11 – Kehrer Bros. Roofing has covered roofs in Quads A, B, D & E Penthouse
- 08/23/11 – East Iowa Deck Supports starts metal panels at the Test Cell Building
- 08/26/11 – Grover Mays & Sons completes Quads F & J roof deck
- 08/26/11 – Kehrer Bros. completes Quads C (high roof), Penthouse &Quad D roofs
- 09/02/11 – Litton Enterprises completes roof storm lines in Quads A, B, C, D & Pent
- 09/19/11 – A & K Specialty starts drywall work in Quads A & B, 2nd floor
- 09/23/11 – Kehrer Bros. Roofing covers Quad C (low roof)
- 09/30/11 Kehrer Bros. Roofing covers Quads J, F & E
- 09/30/11 East Iowa Deck Supports installs Metal Panels to Test Cell Building
- 10/05/11 East Iowa Deck Supports starts Metal Panels to the Education Building
- 10/12/11 Southwestern Sprinkler Service test sprinkler piping in Quads A, B & D
- 11/18/11 E. T. Simonds Construction Company started rocking West of ED Bldg
- 11/21/11 Automotive Technology completes In-Ground Vehicle Lifts
- 11/22/11 Ron Ward Painting starts painting in Quads A & B
- 12/02/11 Kerher Bros. Roofing completes roofing of all buildings
- 12/19/11 Southern Illinois Piping sets Chillers in Outside Mechanical Space
- 01/03/12 Diecker- Terry Masonry start interior block walls in Automotive areas
- 07/17/12 – Substantial Completion
- 10/15/12 – Final Completion
- 12/31/13 – Established Contract End Date